SECTION 3 INSTALLATION
The primary power leads must be insulated copper conductors. Three power leads and one ground wire are re-
quired. Either rubber covered cable or conduit (flexible or solid) may be used. Table 3-1 provides recommended
input conductors and line fuse sizes.
Remove the top cover. Identify primary power input connection block, chassis ground lug, and primary input
terminal board. Refer to Figures 3-3 and 3-4.
When using the provided strain relief, refer to Figure 3-2 for proper cable strip lengths. It is important to follow
the cable strip guide to ensure that if the primary input cable is ever pulled from the strain relief, the input con-
ductors will be pulled from the terminal block before the ground lead is pulled from the ground lug. Thread the
input and ground conductors through the large strain-relief in the rear panel of the power source. Connect the
ground wire to the terminal lug located on the "A" frame support. Connect the primary power leads to terminals
L1, L2, and L3 on the input power block. Secure the strain relief on the input cable.
Check all connections for proper tightness. Ensure all connections are correct and well-insulated.
1.
2.
3.
4.
THE CHASSIS MUST BE CONNECTED TO AN APPROVED ELECTRICAL
GROUND. FAILURE TO DO SO MAY RESULT IN ELECTRICAL SHOCK,
SEVERE BURNS OR DEATH.
Figure 3-1. Typical Installation -
User Supplied 3 Phase Fused Power Disconnect Box with Receptacle and Plug
REAR PANEL VIEW
WARNING